Testing a new #ProjectServer project site template #PS2010 #MSProject #EPM #SP2010 #SharePoint
July 4, 2012 at 12:58 pm | Posted in Administration, Configuration, Customisation, Functionality, Information | 7 CommentsTags: Project 2010, Project Server 2010, PS2010
If you are not aware already, deleting or modifying the default lists and fields in Project Server 2007 and Project Server 2010 can break some default functionality on Project Server. For example updating the Issue and Risk Status field choices, particular the “(1) Active” value will prevent the active Issues and Risks displaying in the Reminders web part on the PWA homepage. Other changes can cause the Reporting WSS sync job to fail in the Project Server queue which causes the WSS Project Sites data not to be current in the Reporting database and OLAP Cube. If you do have any of these issues I did write about a fix around a year ago now, this can be found here: http://pwmather.wordpress.com/2011/06/20/project-server-2010-project-site-default-fields/
Below is a useful set of tests that can be used to test a new Project Server 2010 project site to confirm the default functionality with Project Server still works:
· Create a test project with a few tasks and a project site
· Check you can create a new Issue, set the status to Active and assign to a Project Manager account that has access to the Project Site
· Return to PWA homepage using the Project Manager account and ensure you see 1 active issue assigned
· Click on the new Issue and make sure all links function correctly and you can see the Issue on the Project Site
· Check you can create a new Risk, set the status to Active and assign to a Project Manager account that has access to the Project Site
· Return to PWA homepage using the Project Manager account and ensure you see 1 active risk assigned
· Click on the new Risk and make sure all links function correctly and you can see the Risk on the Project Site
· Edit an Issue and link it to a Project task
· Return to PWA Project Centre, does the Issue indicator appear
· View the Project Details page, does the Issue indicator appear next to the task
· Edit a Risk and link it to a Project task
· Return to PWA Project Centre, does the Risk indicator appear
· View the Project Details page, does the Risk indicator appear next to the task
· Can you upload a document
· Edit a Project Document and link it to a Project task
· Return to PWA Project Centre, does the Document indicator appear
· View the Project Details page, does the Document indicator appear next to the task
· Publish the Project Plan
· Check Reporting job is successful in the Project Server queue
· Build the Project Server OLAP Cube, create a report based on the OlapProjectSharePoint template and confirm the issues and risks appear
· Open the IssuesandRisks sample report and confirm the issues and risks appear
· Check you can delete workspace for the test project
· Check can create a new workspace for the test Project
· Publish the Project Plan
· Check the workspace synchronisation is successful – no errors in the queue
To test other functions in Project Server 2010, take a look at this TechNet link:
7 Comments »
RSS feed for comments on this post. TrackBack URI
Leave a Reply
Blog at WordPress.com. | Theme: Pool by Borja Fernandez.
Entries and comments feeds.
[...] This article has been cross posted from pwmather.wordpress.com (original article) [...]
Pingback by Testing a new #ProjectServer project site template #PS2010 #MSProject #EPM #SP2010 #SharePoint « SharePoint (and Project Server) Shenanigans— July 4, 2012 #
[...] http://pwmather.wordpress.com/2012/07/04/testing-a-new-projectserver-project-site-template-ps2010-ms… Rate this:Share this:TwitterFacebookLike this:LikeBe the first to like this. [...]
Pingback by #ProjectServer Active Issues and Risks on PWA Reminders Web Part #PS2010 #SP2010 #SharePoint « Paul's Project Server Blog— July 13, 2012 #
[...] http://pwmather.wordpress.com/2012/07/04/testing-a-new-projectserver-project-site-template-ps2010-ms… [...]
Pingback by #ProjectServer Active Issues and Risks on PWA Reminders Web Part #PS2010 #SP2010 #SharePoint « SharePoint (and Project Server) Shenanigans— July 13, 2012 #
Hurrah! In the end I got a webpage from where I know how
to genuinely take useful data concerning my study and knowledge.
Comment by Valerie— October 27, 2012 #
Sweet blog! I found it while surfing around on Yahoo News.
Do you have any suggestions on how to get listed in Yahoo News?
I’ve been trying for a while but I never seem to get there! Thank you
Comment by Norma— December 1, 2012 #
My brother suggested I might like this web site.
He was totally right. This post
actually made my day. You cann’t imagine just how much time I had spent for this
info! Thanks!
Comment by www.interpolnyc.com— December 2, 2012 #
Thanks for the nice comments.
Paul
Comment by pwmather— December 5, 2012 #