#ProjectServer 2010 #Excel Services Reports fail to Refresh #Office2013 #SP2010
November 23, 2012 at 3:43 pm | Posted in Administration, Configuration, Functionality, Information | 1 CommentTags: Excel Services, Office 2013, Project 2010, Project Server 2010, PS2010
A quick post to highlight an issue you may face if you have upgraded to Office / Excel 2013. I recently created some Excel reports for Project Server 2010 using Excel 2013. These reports failed to refresh in Excel Services. After a quick check on the connection string in Excel, the provider is MSOLAP.5 rather than the usual MSOLAP.4 provider when using Excel 2010. See below
Excel 2010:
Excel 2013:
The ULS log error is:
The workbook ‘http://vm730:81/pwa/ProjectBICenter/Reports/Actual Work.xlsx’ attempted to access external data using the unsupported provider ‘Provider=MSOLAP.5
The fix is very simple, navigate to Central Admin > Manager Service Applications > Excel Services > Trusted Data Providers then add the MSOLAP.5 provider as below:
1 Comment »
RSS feed for comments on this post. TrackBack URI
Leave a Reply
Blog at WordPress.com. | Theme: Pool by Borja Fernandez.
Entries and comments feeds.
[...] This article has been cross posted from pwmather.wordpress.com (original article) [...]
Pingback by #ProjectServer 2010 #Excel Services Reports fail to Refresh #Office2013 #SP2010 « SharePoint (and Project Server) Shenanigans— November 23, 2012 #