#ProjectOnline new #OData resource path for Resource Demand #Reporting #BI #O365 #PPM

November 22, 2016 at 9:35 am | Posted in Administration, Configuration, Functionality, Information, Reporting | Leave a comment
Tags: , , , , , ,

This post covers a new resource path in the OData endpoint for Microsoft’s PPM tool Project Online to give you the data you need for true resource demand for project assignments and resource engagement assignments. Before resource engagements were introduced, you could have assignments in the project plans or in the resource plans. For reporting, the data was available in the Assignments and the AssignmentTimephasedDataSet resource path feeds, normal project assignments data would be in the AssignmentWork field and resource plan work was in the AssignmentResourcePlanWork field. There was also an AssignmentCombinedWork in the AssignmentTimephasedDataSet feed that displayed the correct resource demand for the resource when you used both resource plans and project plans. The AssignmentCombinedWork field would take into account for the project resource utilisation calculation options. With the introduction of resource engagements there wasn’t a single field that gave you this same resource demand data – until now!

If you regularly view the Project OData service root URL (_api/ProjectData) you might have noticed a new feed, ResourceDemandTimephasedDataSet. This feed has the following properties:

image

The ResourcePlanUtilizationType type will display either a 0, 1 or 2. This is the property to indicate the project resource utilisation calculation options for the project. The enumeration for these values is below:

  • o = Project Plan
  • 1 = Resource Engagements
  • 2 = Project Plan Until

The ResourcePlanUtilizationDate property will only contain a date when the “Project Plan Until” resource utilisation calculation option is set.

This new ResourceDemandTimephasedDataSet feed will show the true resource demand for the project resource utilisation calculation option when using both project assignments and resource engagements. Some scenarios below show when data would and wouldn’t be included in this new feed:

Scenario 1: Project plan has resource assignments and resource engagements. The “Calculate Resource Utilization from:” option is set to Project Plan. In this scenario only the project assignments will be included in the ResourceDemandTimephasedDataSet feed.

Scenario 2: Project plan has resource assignments and resource engagements. The “Calculate Resource Utilization from:” option is set to Resource Engagements. In this scenario only the resource engagement assignments will be included in the ResourceDemandTimephasedDataSet feed.

Scenario 3: Project plan has resource assignments and resource engagements. The project assignments start from the 20th November to the 10th December 2016. The Resource engagements start from the 25th November to the 20th December 2016. The “Calculate Resource Utilization from:” option is set to Project Plan until with a date set to 1st December 2016. In this scenario only the project assignments will be included from the 20th November 2016 up to and including the 1st December 2016 and only resource engagement assignments from the 2nd December to 20th December 2016  will be included in the ResourceDemandTimephasedDataSet feed.

Example data can be seen below:

image

That makes things far easier for reporting resource demand, without this new feed you had to use the AssignmentTimephasedDataSet feed and the EngagementsTimephasedDataSet feed and join the datasets.

#ProjectServer and #SharePoint 2013 / 2016 November 2016 Cumulative Update #PS2013 #SP2013 #PS2016 #SP2016 #MSProject

November 8, 2016 at 9:19 pm | Posted in Administration, CU, Fixes, Functionality, Information | Leave a comment
Tags: , , , , ,

The Office 2016 November 2016 updates and cumulative updates are now available, please see the links below:

https://support.microsoft.com/en-us/kb/3200802

Project 2016 November 2016 update:
https://support.microsoft.com/en-us/kb/3127960

SharePoint Server 2016 / Project Server 2016 November 2016 update:
https://support.microsoft.com/en-us/kb/3127940 & https://support.microsoft.com/en-us/kb/3127942 & https://support.microsoft.com/en-us/kb/2910950

The Office 2013 November 2016 updates and cumulative updates are now available, please see the links below:

https://support.microsoft.com/en-us/kb/3200802

Project Server 2013 November 2016 CU Server Roll up package:
https://support.microsoft.com/en-us/kb/3127931

Project Server 2013 November 2016 update:
https://support.microsoft.com/en-us/kb/3127937

Project 2013 November 2016 update:
https://support.microsoft.com/en-us/kb/3127959

Also worth noting, if you haven’t done so already, install Service Pack 1 http://support2.microsoft.com/kb/2880556 first if installing the November 2016 CU.

As always, fully test these updates on a replica test environment before deploying to production.

Update #ProjectOnline Resource custom field values using #PowerShell with data from #AzureAD user attributes #PPM #Offce365 #ProjectServer #CSOM

November 7, 2016 at 9:40 pm | Posted in Add-on, Administration, Configuration, Customisation, Functionality, Information, PowerShell, Reporting | Leave a comment
Tags: , , , , , , , ,

This blog post will demonstrate a simple example of how Microsoft’s PPM tool, Project Online, can include / sync metadata from Azure AD user attributes to resource custom fields in Project Online. This example script will update the resource custom field “Job Title” on my test tenant with the data from the Azure AD user “Title” attribute.

This script example can be downloaded here: https://gallery.technet.microsoft.com/Update-Online-Resource-83137b7f

The script does require some additional modules / DLLs to work. Firstly you will need the Azure AD module installed, this can be downloaded here: http://connect.microsoft.com/site1164/Downloads/DownloadDetails.aspx?DownloadID=59185. You will also need the SharePoint Online and Project Online CSOM DLLs. The DLL’s used are from the NuGet package here: https://www.nuget.org/packages/Microsoft.SharePointOnline.CSOM/16.1.5521.1200. There are later version available, check here: https://www.nuget.org/packages/Microsoft.SharePointOnline.CSOM. Download those as required. These modules can be seen here on line 3,5 and 14 in the example script, the location will need to be updated to reference the correct location for your SP / PS Online CSOM DLLs.

The user setting up the script will need to update the correct location to the DLLs required, the AD username, AD password, CSV file location, PWA instance URL, username, password and the custom field internal name. The PWA account specified will need edit access to all of the resources in PWA and the AD account will need access to read all the users in Azure AD. Ensure the variables have been updated correctly, placeholder values seen below:

image_thumb.png

In this example all users in the Azure AD will be exported, clearly if you have a large organisation it would be efficient the filter for only those users that exist in Project Online. The code matches users and resources based on the AD display name and PWA resource name when updating the resources in PWA.

To get the correct custom field internal ID I use the REST API, <PWA Site URL> + /_api/ProjectServer/CustomFields. Find the resource level custom field and copy the InternalName as seen below:

image_thumb.png

Once the PowerShell script has been updated, save it and it can then be tested on a test / non-production environment. Once executed in PowerShell, each resource found in the CSV file will be outputted as seen in the example below. In this example there are many AD users in the CSV export that do not exist in the PWA instance.

image_thumb.png

Checking in the Resource Center after the script has run you can see for the resources that exist in the CSV file created, the Job Title has been updated with the values found in Azure AD / the export CSV file:

image_thumb.png

The CSV file generated can be seen here:

image_thumb.png

This PowerShell script could be run on a schedule from a server on-prem or even in Azure / webjob. The script would just need access to save / access a CSV file and the DLLs / modules required. Fully test this script on a test / non-production PWA instance before running on a Production PWA instance.

The script is provided “As is” with no warranties etc.

Update #ProjectOnline Project custom field values using #PowerShell with data from a CSV file #PPM #ProjectServer #CSOM

November 6, 2016 at 4:44 pm | Posted in Add-on, Administration, Configuration, Customisation, Functionality, Information, PowerShell | 1 Comment
Tags: , , , , , , , ,

This blog post will demonstrate a simple example of how Microsoft’s PPM tool, Project Online, can include data from an external system. This is a very simple example using a demo CSV mock up of data that could be from an external system. The CSV part could easily be replaced by a SQL query or a REST API query to the source system etc.

Example CSV data used can be seen below:

image

As you can see, my imagination for example project names has not improved! The code uses the Project Name as the key between the two data sets – the CSV file and PWA so the names will need to match.

This script example can be downloaded here: https://gallery.technet.microsoft.com/Update-Online-Custom-Field-12f034f4

The user setting up the script will need to update the correct location to the DLLs required, the PWA instance URL, username, password, the custom field internal name and the location of the CSV file. The account specified will need edit access to all of the projects in PWA. Ensure the variables have been updated correctly, placeholder values seen below:

image

image

The DLL’s used are from the NuGet package here: https://www.nuget.org/packages/Microsoft.SharePointOnline.CSOM/16.1.5521.1200. There are later version available, check here: https://www.nuget.org/packages/Microsoft.SharePointOnline.CSOM. Download those as required.

The get the correct custom field internal ID I use the REST API, <PWA Site URL> + /_api/ProjectServer/CustomFields. Find the project level custom field and copy the InternalName as seen below:

image

Once the PowerShell script has been updated, save it and it can then be tested on a test / non-production environment. Once executed in PowerShell, each project found in the CSV file will be outputted as seen in the example below. In this example two projects exist in the CSV data but not in my example Project Online PWA instance (remember for this example, the names need to match in the CSV file and PWA):

image

Checking in the Project Center after the script has run you can see for the projects that exist in the CSV file, the project budget includes the values found in the CSV file:

image

This PowerShell script could be run on a schedule from a server on-prem or even in Azure. The script would just need access to the data to import (CSV file etc.) and the DLLs. Fully test this script on a test / non-production PWA instance before running on a Production PWA instance.

The script is provided "As is" with no warranties etc.

Last logon time for the #ProjectOnline PWA users report #PPM #PowerBI #PowerQuery #Office365 #SharePoint #BI part 2

October 12, 2016 at 4:46 pm | Posted in Add-on, Administration, Configuration, Customisation, Functionality, Information, Reporting, Workarounds | Leave a comment
Tags: , , , , ,

This is last post in this mini series for the last connect / last logon feature for Project Online, Microsoft’s PPM tool. In this post we will create the Power BI report. For those that missed the previous post see the links below, check these out first:

Firstly, capturing the last logon time: https://pwmather.wordpress.com/2016/09/30/want-to-capture-the-last-logon-time-for-the-projectonline-pwa-users-ppm-javascript-office365-sharepoint/

Secondly, part 1 of the report creation – setting up the dataset queries in preparation for this post: https://pwmather.wordpress.com/2016/10/10/last-logon-time-for-the-projectonline-pwa-users-report-ppm-powerbi-powerquery-office365-sharepoint-bi-part-1/

If you are continuing where we left off after part 1, open the saved Power BI report:

image

We have the blank canvas ready to add the data and visualisations. In the blog post we I cover creating the report below, Power BI has many options which we don’t cover here but all are intuitive so have a play!

Page 1 – PWAUsage:

image

Page 2 – PWAUserLastConnectDate:

image

Before we start, the report example I created uses a custom visual from the gallery for the Browser filter, this can be downloaded here: https://app.powerbi.com/visuals/show/ChicletSlicer1448559807354 or alternatively just use the default slicer visual like the one used for the Username filter.

Once the custom visual is imported (or choose to use the default slicer), expand the PWAUage dataset, this is the one we will use for this first page:

image

The first visual we will add is the bottom left pie chart for “Logon by Browser”, from the PWAUsage dataset select Browser and Id:

image

It defaults to the Table visualisation, change this to the Pie chart in the Visualizations pane:

image

Drag Id from Details into Values:

image

Drag the visual to the bottom left corner of the page. In the Visualizations settings pane, click the roller to access the settings, here you can change the settings as needed, for example I turned on the Legend and update the Title:

image

The next visualisation to add is the PWA Usage Details table, click anywhere on the page so no visualisations are selected then from the PWAUsage dataset select Browser, Logon Data and Username:

image

By default, the Logon Date will be broken down into the date hierarchy, change this in the visualisation settings, select Logon Date:

image

Move the visualisation to the bottom center of the page and click the Logon Date column to change the order by so the latest date is in the first row:

image

With the visualisation selected, click the roller in the visualisations settings pane to update the settings as needed. I updated the title, the grid settings, the text size for the data and changed the column order:

image

The next visualisation to add is the Hits Per User bar chart, click anywhere on the page so no visualisations are selected then from the PWAUsage dataset select Browser, Id and Username:

image

Change the visualisations from a table to a Stacked bar chart and move Id to Values and Browser to the Legend:

image

Move the visualisation to the center of the page and extend it to the right hand side of the page by dragging it:

image

The same process as before, update the visualisation settings as required by clicking the roller. I updated title, increased the size of the legend text and turned on data labels.

The next visualisation to add is the Last Refresh table, click anywhere on the page so no visualisations are selected then from the PWAUsage dataset select Last Refreshed, resize the visualisation and move it to the top right hand corner of the page:

image

Update the visualisation settings as required by clicking the roller. I added a title and increased the size of the data text:

image

Add a text box to the top of the page and enter the report title, change the settings as required:

image

The next visualisations to add are the cards showing the totals, the process is the same for all so I will only cover adding one in detail. Click anywhere on the page so no visualisations are selected then from the PWAUsage dataset select Id, change the visual from a table to a Card:

image

Move the visual to the bottom right corner of the page, resize it and update the settings as required, I added a title, removed the category label and increased the size of the data label:

image

Add 5 more cards, select the one already created then copy and paste it 5 times then place them in the correct location on the page as required:

image

The 5 additional visualisations need different settings applied as these will show the hits per Browser. To update them, select one so that the settings are visible. Drag Browser from the PWAUsage dataset to the Visual level filters setting:

image

Select IE:

image

Now update the title from Total Hits to Total IE Hits:

image

Repeat this for the other 4 cards but set one for Chrome, Edge, Firefox and Other so you end up with this:

image

The final visualisations to add to this page are the filters, with no visualisation selected, select Username from the PWAUsage dataset, change this from a table to a slicer and change the settings as required. I added a title, turned off the header row, turned of Select all and turned off single select:

image

Now repeat this but select Browser and change it to the Chiclet Slicer:

image

Change the settings as required, I added a title, turned off the header row and set it to have 2 columns:

 image

That is the first page set up, rename the page and it is completed:

image

So here you can see some useful stats around the PWA usage.

Click the + next to the first page to add a new page and rename this to PWAUserLastConnectDate:

image

Now expand the PWALastLogon dataset and select both fields, change the column order so Resource name is first then change the row order so the Resource Name is alphabetical:

image

Change the settings as needed, I added a title, turned off the horizontal grid line and increased the text size. Now add a text box to the page to add the report title:

image

On this page you can quickly see who has logged in and when plus who has never logged in since adding the JavaScript to the Project Web App homepage – unless of course they always by pass the PWA homepage or the pages where you added the JavaScript!

There are lots of options available, have a play and build great dashboards! If you used the Chiclet slicer here is a cool option to add:

image

It supports Image URLs, for this I updated the PWAUsage dataset and added a new column called Browser URL:

image

As you can see this is an if statement, based on the Browser a certain URL is set to display the correct logo for each browser, either save the images to a site you have access to or use images from the internet. Then on the report designer I set the Browser URL to be an Image URL on the Modelling tab:

image

Then update the Chiclet Slicer settings:

image

Once completed save and publish your report to Power BI or you can just use it from Power BI Desktop if needed.

Power BI offers great report visualisations, this is just a simple example, see what you can come up with!

#ProjectServer and #SharePoint 2013 / 2016 October 2016 Cumulative Update #PS2013 #SP2013 #PS2016 #SP2016 #MSProject

October 12, 2016 at 8:42 am | Posted in Administration, CU, Fixes, Functionality, Information | Leave a comment
Tags: , , , , ,

The Office 2016 October 2016 updates and cumulative updates are now available, please see the links below:

https://support.microsoft.com/en-gb/kb/3194160

Project 2016 October 2016 update:
https://support.microsoft.com/en-gb/kb/3118342

SharePoint Server 2016 October 2016 update – Project Server 2016 fixes:
Nothing for Project Server 2016 at the moment

The Office 2013 October 2016 updates and cumulative updates are now available, please see the links below:

https://support.microsoft.com/en-gb/kb/3194160

Project Server 2013 October 2016 CU Server Roll up package:
https://support.microsoft.com/en-gb/kb/3118365

Project Server 2013 October 2016 update:
https://support.microsoft.com/en-gb/kb/3118370

Project 2013 October 2016 update:
https://support.microsoft.com/en-gb/kb/3118351

Also worth noting, if you haven’t done so already, install Service Pack 1 http://support2.microsoft.com/kb/2880556 first if installing the October 2016 CU.

For more details see: https://blogs.technet.microsoft.com/projectsupport/2016/10/12/project-and-project-server-october-2016-updates-released/

As always, fully test these updates on a replica test environment before deploying to production.

Last logon time for the #ProjectOnline PWA users report #PPM #PowerBI #PowerQuery #Office365 #SharePoint #BI part 1

October 10, 2016 at 4:21 pm | Posted in Add-on, Administration, Configuration, Customisation, Functionality, Information, Reporting, Workarounds | 2 Comments
Tags: , , , , ,

Following on from my last post where I published an option / workaround for the last connected feature that has been removed from Project Online, this post will look at generating a Power BI report for the usage data that is captured. For those of you that missed the last post, see link below before continuing:

https://pwmather.wordpress.com/2016/09/30/want-to-capture-the-last-logon-time-for-the-projectonline-pwa-users-ppm-javascript-office365-sharepoint/

Now that we have some data captured in the list we can generate a report, for this example report I have used Power BI and Power Query but you could do something similar in Excel Power View with Power Query or even JavaScript / HTML if you really wanted to. In this post I will walkthrough all the steps needed to start creating the example report seen below:

Page 1 (PWAUsage):

image

Page 2 (PWAUserLastConnect):

image

So firstly we need to two URLs for the data used to generate this report, the first one is from the PWAUsageList, this assumes the list is called PWAUsageList, update the URL as needed:

<PWA URL>/_api/Web/Lists/GetByTitle('PWAUsageList')/Items()?$Select=WhoString,LogonDate,Browser,Id

The next one is from the Project OData Reporting API to return the active users that have an account:

<PWA URL>/_api/ProjectData/Resources()?$Filter=ResourceIsActive eq true and ResourceNTAccount ne null

Now launch Power Bi Desktop and click Get Data > OData Feed:

image

Enter the URL for the PWAUsageList as seen in the example above and click OK then click the Edit button on the preview window and the Query Editor window will open. Change the Query name from Query1 to something meaningful such as PWAUsage. Now change the LogonDate Column to Date rather than Date/TIme by right clicking on the column heading > Change Type > Date:

image

Also rename any columns as needed and remove the duplicate ID column, I renamed LogonDate to Logon Date and WhoString to Username:

image

Now we will add a custom column to this query to get the “Last Refresh” date. To do this click the “Add Column” ribbon then “Add Custom Column” and complete the details:

image 

Click OK and the dataset will update:

image

Now we need to add the Resources data source, in the query editor click Home > New Source > OData Feed and enter the Resources OData URL as seen in the example above and click OK then click OK on the data preview window. Now click Choose Columns, the only column needed is ResourceName:

image

Click OK. The ResourceName column was then renamed and the Query renamed too:

image

Now we need to create a third query table that contains data from the PWAUsage query and the ActivePWAUsers query to show the last logon time for each PWA User. We could keep just the two queries and merge the two without creating a third table but that is up to you, you would just chose the Merge Queries option if you wanted to have just two queries. For this post I will create a third dataset query. In the query editor click the Merge Queries > Merge Queries as New option:

image

ActivePWAUsers in the top table and PWAUsage is the bottom table, select Resource Name in the top section and Username in the bottom section. The default join kind is fine for this merge:

image

Click OK. Update the query name to something meaningful such as PWALastLogon.

image

Click the Expand button next to the NewColumn:

image

Change the radio button to Aggregate and then click the dropdown next to Logon Date and select Maximum, don’t select anything else:

image

Uncheck the option “Use original column name as prefix” then click OK:

image

Rename the new column to remove the “Max of” and call the column “Latest Logon Date”

We now have the three queries ready to load into the report:

image

Now click Close & Apply > Close & Apply from the Home ribbon menu and the report will show your queries available:

image

The first thing to do will be to ensure the relationships between the three datasets is correct. Click the relationships button from the left navigation and update as needed:

image

All I had to change was to join PWAUsage to ActivePWAUsers by dragging Username from PWAUsage to Resource Name in ActivePWAUsers.

Now click back to the report view and we are ready to design the report. Now we have the datasets ready, in part 2 we will look at creating and designing the report, for now ensure you save the Power BI report for later when we look at designing the report.

#ProjectServer / #ProjectOnline error opening Enterprise Resource Pool #MSProject #Office365 #PPM

October 10, 2016 at 8:17 am | Posted in Administration, Functionality, Information, Issue, Workarounds | Leave a comment
Tags: , , , , ,

A quick post to highlight an issue and workaround for opening the Enterprise Resource Pool in Project Pro using the Open button on the Resources tab in the Resource Center:

image

If you try and click the Open button with no resources selected in the grid you will get the error below:

“This action couldn’t be performed because Office doesn’t recognize the command it was given” :

image

Select at least one resource in the grid then this command will work fine.

Want to capture the last logon time for the #ProjectOnline PWA users? #PPM #JavaScript #Office365 #SharePoint

September 30, 2016 at 2:19 pm | Posted in Add-on, Administration, Configuration, Customisation, Functionality, Information, Reporting | 2 Comments
Tags: , , , ,

This is a supporting blog post for a new JavaScript file I have published to the Microsoft Gallery, it can be downloaded here:

https://gallery.technet.microsoft.com/Capture-Online-user-last-43621a21

Microsoft recently removed the Last Logon details from the Manage Users page in PWA settings for Project Online – Microsoft’s PPM tool. This simple script is an alternative solution that will capture the last logon for the Project Web App users. It wont capture the last logon from Project Professional or if a user accesses the API’s etc., it will only capture the last logon from the page the script is added to. In this example I have added the script to the homepage, so if a user has the Project Center saved as a favourite link and bypasses the PWA homepage then their logon would not be captured. You could add the script to multiple PWA pages if required.

When a user accesses the PWA homepage for the first time that day, an item is created on the SharePoint list in the PWA site, it only captures the logon once per day. See an example on my demo instance:

image

It captures the user name, the logon data and the browser that was used. This list will need to be created manually with the following details:

List Name: PWAUsageList

Columns:

image

The LogonDate column setting defaults to Today:

image

Once the list is set up, upload the JavaScript file to a library on the PWA site then the script can be added to the PWA homepage using a content editor web part:

image

Reference the location of the PWAUsage.js file – in this example I added the JavaScript file to the Shared Document library in the PWA site, also notice the Chrome Type is set to None so nothing is visible on the PWA homepage.

That is it, it will now capture the users who access the PWA homepage. Once you have the data on the list you can then create a report for that data. I will publish a blog post in the next week or so that details this but for now here is an example report screen shot in Power BI:

image

Fully test this on a non-production PWA instance before rolling out to Production, the script is provided As Is with no warranties etc. Try it out and let me know what you think.

#Office365 Project Time Reporter mobile app for #iOS released #ProjectOnline #PPM #Timetracking

September 21, 2016 at 10:49 am | Posted in Add-on, Administration, App, Functionality, Information, Mobile | Leave a comment
Tags: , , , , ,

Yesterday saw the release of the Office 365 Project Time Reporter mobile app for Apple’s iOS, see the announcement here: https://blogs.office.com/2016/09/20/announcing-the-availability-of-office-365-project-time-reporter/

This post gives a walkthrough on getting started and using the app on your iOS device. Firstly download the app for your iOS device from the Apple store:

appstore

Once completed locate the Project Time Reporter app:

app icon

On first launch you will be required to enter the Project Online PWA URL:

splashscreen

You will then see the login screen:

login

Enter your Office 365 credentials and click Sign In and you will see the loading screen briefly whilst the data is loaded:

loading

Once completed you will see the Timesheet for this period:

timeesheet

From here you can enter the actuals as needed. Using the green control menu at the bottom of the app you can scroll between timesheet periods using the previous and next buttons, add a row, save the timesheet, send the timesheet or filter the projects. Using the ellipsis in the top right hand corner you can access other timesheet options such as refresh, go to current period, summary, send progress for all tasks or manage timesheets. The app menu in the top left corner enables you to access the app settings, here you can switch to the tasks view or see the app settings. Below you will see screen shots of some of these features.

Firstly the app menu screen, here you can view Timesheet, Tasks or Settings:

app menu

On Settings you can view the PWA URL and username and turn on two options:

app settings

I turned on the planned time in my app:

timesheet with planned work

To enter time just click in the box for the day you want to add time to:

timesheet actuals

You can use the Save button on the green menu at the bottom of the app to save the timesheet or send the timesheet using the send button. If you have many projects on the current timesheet you can using the filter option:

filter projects

If you want to send progress, click the ellipsis in the top right corner:

timesheet options

Here you will also see other options such as Summary:

timesheet summary

Manage Timesheets:

manage timesheets

On the timesheet view you can add rows using the Add button on the green menu:

add row in TS

We have focused on the Timesheet view here but there is also a Tasks view that is accessible from the app menu > Tasks:

tasks

You can change the view by clicking the Current Tasks heading:

task views

You can access the task options to filter and sort the tasks using the ellipsis in the top right hand corner:

task options

Selecting a task will take you to the task details screen:

taskscreen

To edit a task click Edit in the top right hand corner:

edittasks

Make any changes as needed and click Save or Send.

Download it today and see what you think – it will make the timesheet / task update process so easy when you are on the move!

Next Page »

Blog at WordPress.com.
Entries and comments feeds.